MS Non-working HELP!
Hi Ignacio, thank you for your reply but unfortunately this doesn't resolve my issue.
The programme calendar I am currently working on is set as 24 hours which allows me to add bars over the top of the grey. This shows that although its a weekend and 'technically' non working, we are in fact working both Saturday and Sunday. What I am struggling with is adding the Christmas period 23/12/24 - 03/01/24 as non-working and it shown as non-working i.e. all greyed out on the same programme as the weekend work.
- Ignacio_MartinNov 11, 2024Iron Contributor
Hi again Ames
I assume then that you have assigned the 24 Hours calendar to the project and you are displaying the Standard calendar in the Timescale. If so, you can define the Christmas period 23/12/24 - 03/01/24 as non-working time in the Exceptions tab (Menu bar > Project > Properties > Change Working Time... for Standard Calendar) and OK.
If it is not displayed immediately, try refreshing the screen, simply select the Gantt Chart view again
We look forward to your feedback.
Ignacio