MS Non-working HELP!
Hi all, I desperately need help. I am currently working on a 24 hour programme where if you work on a weekend the bar is on top of the grey. On the same programme, my Boss wants to 'grey out' the Chr...
Ignacio_Martin
Nov 11, 2024Steel Contributor
Hi Ames.
On the Menu bar > Gantt Chart Format > Zoom > Timescale: > Timescale... > Non-working time tab (or double-click on the Gantt-Timescale header), you can specify a single calendar to be represented on the Gantt. By default, it is the Standard one, but you can change it to 24 Hours or something else. Also on that tab, you can choose the Color and Pattern of the non-working time, even choosing to have it displayed In front of task bars.
These changes do not affect the schedule, just the presentation of the Gantt, and remember that you can only display one calendar on the chart.
I hope I have helped you.
Ignacio Martín