Migration from 2013->2019 - Project site selection not possible

Hello,

after migrating from Project Server 2013 to Project Server 2019 I found this strange behavior for Enterprise Project Types:

The dropdown field for selecting the Project Site Template language and Template is not populated - not with the template used in Project Server 2013 (which is not working) and not with the Standard Project Site or a newly created Project Site Template.

The templates (old and new) can be found as activated in the Solutions Gallery and I can generate a new Subsite using the standard Project Site template as well as using the new template.

Any ideas?

  • Hello TamaraF ,

    Try the following:

    • Arrange a system outage
      • Assuming the system is live etc.
    • Backup the content database where the PWA site collection is hosted
      • Just in case something goes wrong, you can restore the database backup
    • Run the following PowerShell command: Disable-SPFeature pwasite -Url <URL>
    • Run the following PowerShell command: Enable-SPFeature pwasite -Url <URL>

    See if that resolves the issue.

    Paul

2 Replies

  • Hello TamaraF ,

    Try the following:

    • Arrange a system outage
      • Assuming the system is live etc.
    • Backup the content database where the PWA site collection is hosted
      • Just in case something goes wrong, you can restore the database backup
    • Run the following PowerShell command: Disable-SPFeature pwasite -Url <URL>
    • Run the following PowerShell command: Enable-SPFeature pwasite -Url <URL>

    See if that resolves the issue.

    Paul

    • TamaraF's avatar
      TamaraF
      Brass Contributor
      Thanks, Paul. That did the trick - the Project Site templates are now back in the dropdown!