Migrate a project in Project Plan 1 into Project Plan 3
- Sep 29, 2023Thank you Paul for the fast answer: at least a small help: export plan 1 to xls. Open new project in plan 3, copy the whole column with text, duration, date, etc etc. one by one and paste it into the new project. At least the gant chart, text etc can be used again including interdependency of different tasks. , Then adapt structure etc.
Hi Paul_Mather, actually I have no idea 🙂
Project 1 is on https://project.microsoft.com/etcetera en Project 3 is on "companyname".SharePoint.com.
Issue is that I've figured out that Project 3 has more features (like saving as pdf) and Project 1 not.
I would like to do 2 things:
1) import my already entered file in Project 1 in Project 3 (so I don't have to type over all the tasks)
2) new file in Project 3 save/export somewhere else (e.g. Onedrive as a file or on a stick)
Also, what is the difference between "companyname".SharePoint.com and "companyname"-my.SharePoint.com??
- Paul_MatherApr 15, 2020MVP
Hello annemarl1 ,
Unfortunately there is no way to migrate / export a project plan from Project for the web into Project Online Project Web App.
Paul
- annemarl1Apr 15, 2020Copper Contributor😞
And when entered a new projectplan into Project Online Project Web App, can I somehow export this to my OneDrive, or someone elses Project Web App or save this on a stick?
And can you please explain the difference between the two SharePoints?
Thanks 🙂- Paul_MatherApr 16, 2020MVP
Hello annemarl1,
A Project for the web project can't be exported to a file.
company.sharepoint.com is the main tenant, company-my.sharepoint.com is the personal sites like the classic My Sites in previous versions of SharePoint - this is where your personal OneDrive is etc.
Paul