Migrate a project in Project Plan 1 into Project Plan 3

Can anyone inform me how to migrate a project created in Project Plan 1 (SharePoint Online Plan) into Project Plan 3 (Project Web App)? Or isn't that possible? It seems I cannot download or copy/pas...
  • Peter_Roethlisberger's avatar
    Peter_Roethlisberger
    Sep 29, 2023
    Thank you Paul for the fast answer: at least a small help: export plan 1 to xls. Open new project in plan 3, copy the whole column with text, duration, date, etc etc. one by one and paste it into the new project. At least the gant chart, text etc can be used again including interdependency of different tasks. , Then adapt structure etc.