Microsoft Projects timeline not working correctly?
Hey there, I have been looking high and low for an answer on this, but cannot seem to find an answer anywhere. I have set non-working times in my calendar. They are showing in the timeline but ac...
Miles_Goodchild
Jan 04, 2021Brass Contributor
Are the resources assigned to the tasks using that calendar? If they're using another calendar then they will be allowed to operate in the manner you describe. I am assuming you haven't set the constraints to a "must" type of course.