Microsoft Project
Hi all, How to eliminate any resource constraints by changing the number of work resources to a number of your choice in MS project? Thanks, K
Ignacio_Martin
Feb 08, 2023Iron Contributor
If you mean to avoid overallocated resources of Type Work, you can enter in the Max. Units column of the Resource Sheet view, a very high number of resources available in your project, for example 99999.