Hello Utkarsh1919 ,
Please can you advise if you are using Microsoft Project Desktop app standalone without Project Online etc.? If this is the case, Power BI can not directly access the data stored in mpp files.
Paul
Paul_Mather thanks a lot for helping out. We will be using Microsoft Project Desktop app as we have to add custom columns which will be around 40-50 nos. and this custom column data we want it on PowerBI
- Paul_MatherMay 08, 2024MVP
Hello Utkarsh1919 ,
As you are using the standalone Microsoft Project desktop app that just saves data to mpp files, you'd need to find / build a solution that pushed the data from the Microsoft Project Desktop client into a central data storage that Power BI can access such as Azure SQL DBs, Data verse, SharePoint lists etc. Or look to use Microsoft Project Online, you can then use the Project Online reporting APIs in Power BI to get the data out for reports.