Forum Discussion
NKumar2010
Nov 03, 2022Brass Contributor
Merging two schedules
Hi, I maintain a large program schedule (superset) in MS Project. The program has multiple contractors, each having their individual schedules (subset) & these schedule form a subset of the larger...
NKumar2010
Nov 04, 2022Brass Contributor
Hi John,
Yes, contractor's plans are also in Project. I am not too sure of the version, but I reckon, the solution can be independent of the version.
The tasks in the contractor plan are also shown in my plan. My plan has many phases and contractor's plan is included in one of the phases (say, construction phase). There are some organizational milestones within the construction phase, so I can't directly copy paste entire contractor's schedule inside construction phase. Its like within construction phase, a set of tasks from contractor's schedules, then few organizational approvals & milestones, then a few more of contractor's schedule and then a few more organizational approvals. This cycle repeats until construction phase is over.
Mostly each contractor's schedule is independent of other contractor's schedule.
Hope this provides some more clarity to the situation
Yes, contractor's plans are also in Project. I am not too sure of the version, but I reckon, the solution can be independent of the version.
The tasks in the contractor plan are also shown in my plan. My plan has many phases and contractor's plan is included in one of the phases (say, construction phase). There are some organizational milestones within the construction phase, so I can't directly copy paste entire contractor's schedule inside construction phase. Its like within construction phase, a set of tasks from contractor's schedules, then few organizational approvals & milestones, then a few more of contractor's schedule and then a few more organizational approvals. This cycle repeats until construction phase is over.
Mostly each contractor's schedule is independent of other contractor's schedule.
Hope this provides some more clarity to the situation
John-project
Nov 04, 2022Silver Contributor
NKumar2010,
How do the contractor schedules account for the organizational approvals and milestones? For example, do the contractor schedules have a "holding period task" while waiting for an approval?
In your schedule do you set up dependencies between their tasks and your organizational tasks? For example, let's say the contractor completes tasks "A", "B" and "C" but then needs an approval before proceeding. How do you model that in your plan? Then how do you relate that to the contractor?
From what you told me so far I think your best bet is to use the static master approach. It may require some rethinking on your part to set up the master (superset) structure but the other approach goes back to the copy/paste/review/revise process which involves a lot of time and redundancy.
John
How do the contractor schedules account for the organizational approvals and milestones? For example, do the contractor schedules have a "holding period task" while waiting for an approval?
In your schedule do you set up dependencies between their tasks and your organizational tasks? For example, let's say the contractor completes tasks "A", "B" and "C" but then needs an approval before proceeding. How do you model that in your plan? Then how do you relate that to the contractor?
From what you told me so far I think your best bet is to use the static master approach. It may require some rethinking on your part to set up the master (superset) structure but the other approach goes back to the copy/paste/review/revise process which involves a lot of time and redundancy.
John