Merging Subprojects

We've recently been asked to combine our individual schedules into master files prior to delivering to the customer. Each sub schedule contains data in the Outline Codes (OC). However, upon inserting...
  • John-project's avatar
    Jan 02, 2025

    RCook1959,

    Custom Outline Code fields are unique to a file. When you insert a subproject into a master (unlinked), the master does not contain the same custom Outline Code field so you will have to do an end around run. Here are a couple of choices.

    1. Transfer the Outline Code field to a Text field (e.g. Text1) with a simple copy and paste. The Text field will transfer when you create the static master so just use that at master level.
    2. If you really want the data to exist as an Outline Field in the static master, do three things. First, copy the Outline Code field in each subproject into a Text field as in step one. Two, use the Organizer to transfer the custom Outline Code from each subproject to the master (Note, you will need to do this one at a time for each subproject if the same Outline Code field is used but with different values in each subproject). Three, use the Text field data at master level to select the Outline Code at master level.

    Easy and convenient? Yeah, not so much but sometimes you just gotta punt.

    John