Material Assignment Contour is Changed after Upgrade (2010 to 2019)

Hello, We are upgrading the server from 2010 to 2019 (Project Pro 2016). We noticed a task that has 2 resources - 1 work resource and 1 material resource. We researched it in 4 places: Project P...
  • John-project's avatar
    Mar 07, 2021
    First of all, there is no material work, material is a consumable. Yeah I know, when you look at a material assignment row in a Usage view, it shows as "work" but it is not. Material is assigned as a quantity of something like gallons of fuel, number of bricks, reams of paper, etc. A material resource is linearly spread over the full task duration, assuming it is "prorated", although it can also be manually edited for any time span. In your case however, the material time span is greater than that of the work resource which makes no sense. I can only assume it is an assignment corruption that was corrected when you converted to Project 2016.

    Hope this helps.
    John

Resources