Forum Discussion

Clay-Project's avatar
Clay-Project
Copper Contributor
Aug 29, 2022

Mark on Track only changes Task to 99%

Hello,

 

I have a task with 2 resources. 1 resource has baseline work of 10hrs and remaining work of 0hrs. The 2nd resource has baseline work of 0hrs and remaining work of 10hrs. When I "Mark on Track", the resource with remaining work goes to 100% complete and the remaining work switches to actual work of 10hrs. The resource with baseline work remains at 0% complete though resulting in the task being at 99% complete. Why does the Mark on Track option not mark both resources at 100%?

 

Thank you!

  • John-project's avatar
    John-project
    Aug 31, 2022
    Clay-Project,
    I get the same result you do and indeed it looks like a glitch (e.g. bug). Ah, but first impressions can be deceiving. Percent Complete is simply Actual Duration / Duration and examining the values of both variables, they are each 11520 minutes with Remaining duration at zero. Seems like a slam dunk for a "bug".

    However, I do notice, the first resource does show an actual start, so maybe he showed up for the meeting and then was ushered out. Given that, the first resource "started" but never finished (i.e. Actual Finish shows as "NA"). That's why, despite the math, Project is showing an incomplete (i.e. 99%) for the task. Simple solution, either remove the first resource entirely, or show an actual finish. Boom! Problem (and apparent, but false, "glitch") solved.

    John
  • John-project's avatar
    John-project
    Silver Contributor
    ClayThompson,
    Okay help us out here. I think you are misusing the term "baseline work" and hopefully you really mean "work". Baseline values are static values stored in separate baseline fields when a baseline is set, although baseline data can be manually entered. So, when you say resource 2 has zero hours of baseline work yet remaining work of 10 hours, it doesn't make a lot of sense.

    I think a screen shot (Task Usage would be good) showing the task with assigned resources, and these fields: Baseline Work, Work, Remaining Work, % Work Complete, Start, Actual Start, Finish, Duration and Peak. We also need to know your Status Date.

    John
    • Clay-Project's avatar
      Clay-Project
      Copper Contributor

      Good Morning,

       

      Sorry about that. Please see screenshots below. 

      *We set the baseline with one resource and then reassign the work/remaining work to another resource.

       

      Before Mark On Track:

      After Mark on Track:

       

       

      • John-project's avatar
        John-project
        Silver Contributor
        Clay-Project,
        I get the same result you do and indeed it looks like a glitch (e.g. bug). Ah, but first impressions can be deceiving. Percent Complete is simply Actual Duration / Duration and examining the values of both variables, they are each 11520 minutes with Remaining duration at zero. Seems like a slam dunk for a "bug".

        However, I do notice, the first resource does show an actual start, so maybe he showed up for the meeting and then was ushered out. Given that, the first resource "started" but never finished (i.e. Actual Finish shows as "NA"). That's why, despite the math, Project is showing an incomplete (i.e. 99%) for the task. Simple solution, either remove the first resource entirely, or show an actual finish. Boom! Problem (and apparent, but false, "glitch") solved.

        John