Managing a big-scale, cross-organizational project with MS Project
Hello everyone, I'm a consultant assisting our customer as Project Management Office (PMO). Our customer is facing a strategic project with over 800 tasks and milestones and 11 project co-leads from...
Nov 23, 2022
John --
Good question about a perplexing problem. Based on my use of OneDrive, I suspect your problem is with OneDrive and NOT with Microsoft Project. After a PM edits a project, saves it to OneDrive, and then closes the project, OneDrive needs to "sync" these changes to everyone who has access to this project. I have actually seen duplicate projects myself in projects saved to OneDrive.
Because you have so many people who need to open and edit your project, I would recommend that you save this project to a shared network drive rather than to OneDrive. I believe that would totally resolve your problems. If you do not have a shared network drive available for use, you are stuck with the OneDrive application and all of its quirkiness. Hope this helps.
Good question about a perplexing problem. Based on my use of OneDrive, I suspect your problem is with OneDrive and NOT with Microsoft Project. After a PM edits a project, saves it to OneDrive, and then closes the project, OneDrive needs to "sync" these changes to everyone who has access to this project. I have actually seen duplicate projects myself in projects saved to OneDrive.
Because you have so many people who need to open and edit your project, I would recommend that you save this project to a shared network drive rather than to OneDrive. I believe that would totally resolve your problems. If you do not have a shared network drive available for use, you are stuck with the OneDrive application and all of its quirkiness. Hope this helps.
JohnRothbaum
Jan 30, 2023Copper Contributor
Hello guys,
thank you very much for your quick and thorough reply. And sorry for the late response on my behalf!
Your feedback was very valuable and helped us decide on what to do with our plan. We made the decision to continue with the plan under my administration with the other team members being able to view the plan and give me feedback in case any changes are necessary. This seems to be the easiest and safest option.
Thanks again for your valuable input, best regards from Germany.
Cheers,
John
- John-projectJan 30, 2023Silver Contributor
- Jan 30, 2023John --
Thank you for the kind comments. You are more than welcome for the help, my friend!