Making effort calculations work in Project for the Web (P4W)
Dear all, we are having a hard time with "efforts" in P4W since the system is directly calculating the hours based on the number of assigned resources and the duration of the task. This does not re...
Jun 29, 2022
Costas --
I did some testing on this using our organization's Project for the Web instance. I did the following:
1. Set the Duration for each task.
2. Assigned one or more resources to each task. Project for the Web calculated the Effort, based on the assumption that the assigned resources are working full-time (8 hours per day) on each task.
3. Change the Effort value to indicate that the resource will not be working full-time. Project for the Web DID NOT change the Duration.
4. Increased the Duration for one of the tasks. Project for the Web increased the Effort proportionately, but did not go back to assigning the resources to work full-time.
This appears to be new behavior that I have not seen previously, and might indicate your problem has been solved, at least in the version of Project for the Web our organization is using. Just a thought. Hope this helps.
I did some testing on this using our organization's Project for the Web instance. I did the following:
1. Set the Duration for each task.
2. Assigned one or more resources to each task. Project for the Web calculated the Effort, based on the assumption that the assigned resources are working full-time (8 hours per day) on each task.
3. Change the Effort value to indicate that the resource will not be working full-time. Project for the Web DID NOT change the Duration.
4. Increased the Duration for one of the tasks. Project for the Web increased the Effort proportionately, but did not go back to assigning the resources to work full-time.
This appears to be new behavior that I have not seen previously, and might indicate your problem has been solved, at least in the version of Project for the Web our organization is using. Just a thought. Hope this helps.
Costas Constantinou
Jun 29, 2022Brass Contributor
Dale,
Thank you for the reply. What I 'm looking for is to keep the effort from changing while doing changes to other aspects. For instance when trying to change the person assigned to the task the effort is changing. Or when we change the duration it changes the effort. In our organization people may work on multiple tasks at the same time and wait on each other for information (we are a multidiscipline engineering company) so effort is not tightly connected to duration.
Thank you for the reply. What I 'm looking for is to keep the effort from changing while doing changes to other aspects. For instance when trying to change the person assigned to the task the effort is changing. Or when we change the duration it changes the effort. In our organization people may work on multiple tasks at the same time and wait on each other for information (we are a multidiscipline engineering company) so effort is not tightly connected to duration.
- Jun 29, 2022Costas --
As currently configured, Project for the Web fixes or "locks" the Duration that you enter for each task. This is known as Fixed Duration tasks. There is no way to currently fix or "lock" the Effort value. This is a limitation of the tool, at least as for now. Sorry for the bad news. Project for the Web is a very low-level tools designed to manage small and simple projects. If you want expanded functionality, you would probably need to use the Microsoft Project desktop application instead. Hope this helps.- Costas ConstantinouJun 29, 2022Brass ContributorIt does help, thanks. We will be having a custom field and type in the effort hours so we remember what it was. We would have to manually re-enter the effort if the program recalculates.
- Jun 29, 2022Costas --
I applaud you for your creative solution, my friend!