Looking for some advice on calendars / scheduling around holidays

Hello All,   So, we've got two christmas calendars:   Ours - late December to early Jan Site - Mid December to slightly later Jan   My project's standard calendar that i try to use for all act...
  • John-project's avatar
    Sep 19, 2023
    dc_27,
    You are correct. The only real option is to create two separate custom calendars for each of the Christmas breaks. Then apply those calendars to individual tasks.

    Hope this helps.
    John