Linking a value in an Excel cell to a cell in Project

Hello all! We link numerical values from Excel to Project (we use percent complete worksheets in Excel that post to "% Work" rows in Project). This works okay and updates in real time (as soon as th...
  • John-project's avatar
    Jul 22, 2021

    Allen_Hodge 

    You are using Paste Links to link Excel data to Project and I must warn you that paste links are fragile and prone to corruption. If they seem to be working for you I'd say you are very lucky.

     

    With paste links there is no clear method for seeing both "source" and "destination" in the Edit LInks window. You can click on a link in Project and hit "open source" and you will be shown which Excel cell is the source, but it's a "hunt and peck" process. It may be possible to automate a "seek and find" process with VBA but a much better way to accomplish what you are doing is with VBA itself (i.e. no paste links).

     

    However, since you are only importing percent complete, have you tried an import map?

     

    John