Forum Discussion

Molalenge's avatar
Molalenge
Brass Contributor
Aug 06, 2024
Solved

Linking a project to a porfolio

We have five project portfolios consisting of 7-25 sub-projects. Recently, we added a project online to our desktop 2019 version to allow project managers access to their project files. In the past, ...
  • Dale_HowardMVP's avatar
    Aug 06, 2024
    Molalenge --

    When you use the term portfolio, I assume you mean master projects. If this is the case, you will need to delete the master projects and then recreate each of them in Project Online from a new enterprise project file. I am assuming that the subprojects are all stored in Project Online as well. Hope this helps.

Resources