link action for start and duration

Hi,

I have two similar action made by different resources. Is there any way to link to another action both start and duration?

 

I mean:
Action A start on 1/Jan/2022 and its duration is 20 days
Action B needs to have Action A as predecessor by "Start-Start". If I change duration of Action A, also Action B will be updated.

 

Thank you

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor
    Dariocg,
    Sorry no, the Duration field cannot be linked other than through a Paste Link, which I strongly do NOT recommend, or with VBA.

    John