Forum Discussion
Limiting Resources
- Nov 27, 2024
Gordon --
Navigate to the Resource Sheet view and set the Max. Units value to 80% for Resource B. Apply the Gantt Chart view, and select the task to which want to assign Resource B. Right-click in the white or gray part of the Gantt Chart screen and select the Show Split item on the shortcut menu. In the bottom pane (Task Form pane), select Resource B, set the Units value for that resource to 80%, and then enter 80 hours in the Work field. In the Task Form pane, click the OK button. Bingo. You should now see a Duration of 12.5 days, which is the 2.5 weeks that you should expect (your 2.67 Duration is incorrect, BTW). Hope this helps.
Never mind. Found it. In my attempts to work out the original problem, I'd created a reduced hours calendar that was still in the works. That compounded the reduction, resulting in the 5.6hrs.