Forum Discussion

Gordon_Smith's avatar
Gordon_Smith
Copper Contributor
Nov 27, 2024
Solved

Limiting Resources

I have a project that has two types of resources.  One can provide 100% effort to the project (Resource A), and another only 80% (Resource B).  I am setting the work effort, and trying to ensure that...
  • Dale_HowardMVP's avatar
    Nov 27, 2024

    Gordon --

    Navigate to the Resource Sheet view and set the Max. Units value to 80% for Resource B.  Apply the Gantt Chart view, and select the task to which want to assign Resource B.  Right-click in the white or gray part of the Gantt Chart screen and select the Show Split item on the shortcut menu.  In the bottom pane (Task Form pane), select Resource B, set the Units value for that resource to 80%, and then enter 80 hours in the Work field.  In the Task Form pane, click the OK button.  Bingo.  You should now see a Duration of 12.5 days, which is the 2.5 weeks that you should expect (your 2.67 Duration is incorrect, BTW).  Hope this helps.

Resources