Length of days!
I am wanting to use Project to help me plan the courses that I teach in college. I started to play around and have watched various help videos and it looks like a powerful, easy to use piece of soft...
- Feb 26, 2023
Entering task durations in hours is the ONLY way you will be able to set up your class scheduling. And you will also need to create the custom project calendar I outlined.
John
C-J-B
Feb 26, 2023Copper Contributor
Hello John. Thanks so much for this. Really appreciate your help. Although it sounds like Project is not as easy to use as I thought. My work has got it so it looks like the only option for this kind of work so I will try stick with it. So with what you have shown me do I take it that I should then be able to say for each task the length of time in hours rather than days? Would this then make it simpler to enter the length of each task?
John-project
Feb 26, 2023Silver Contributor
Entering task durations in hours is the ONLY way you will be able to set up your class scheduling. And you will also need to create the custom project calendar I outlined.
John
- C-J-BFeb 26, 2023Copper ContributorMany thanks John
- John-projectFeb 26, 2023Silver ContributorC-J-B,
You're welcome and thanks for the feedback.
John