Length of days!

I am wanting to use Project to help me plan the courses that I teach in college. I started to play around  and have watched various help videos and it looks like a powerful, easy to use piece of soft...
  • John-project's avatar
    John-project
    Feb 26, 2023

    C-J-B 

    Entering task durations in hours is the ONLY way you will be able to set up your class scheduling. And you will also need to create the custom project calendar I outlined.

     