Forum Discussion
Last Saved Project Baseline date stored on SQL database
Hello Ana-S ,
An old blog post I wrote but this should help:
https://pwmather.wordpress.com/2011/08/20/report-on-project-server-baseline-save-dates-projectserver-ps2003-ps2007-ps2010-msproject-epm/
Paul
- Ana-SApr 15, 2024Brass Contributor
Thank you so much Paul_Mather . Appreciate your response. I looked at the article and VB macro is used to store last saved baseline date in custom fields. That is a neat workaround.
Is there any way to know how it is showing the last saved date on PWA? It must store this data somewhere on the SQL database. Will the workaround work if the baseline is set through PWA?
- Paul_MatherApr 15, 2024MVP
Hello Ana-S ,
No it won't work for baselines created in the PWA UI. The out of the box date is not available to query in a supported way in the DB as it is not in the reporting schema.
Paul
- Ana-SApr 15, 2024Brass ContributorOh I see. Wish they published that information so we could pick that information on our SSRS. Even if it stored in published or draft schema, it would be easy to pick without putting workaround.
Thank you Paul.