Forum Discussion
Alison Howes
Nov 18, 2019Copper Contributor
Last Published vs Last Modified
Hello, I am struggling with something I thought would be straight forward enough, but seems it isn't! Basically I want to compare Last Modified and Last Published and show a KPI for variance. I...
Paul_Mather
Nov 19, 2019MVP
Hi Alison Howes,
You are better off doing this as a calculation in a report as the PWA calculated fields will not update until the projects are modified and this wont be visible in PWA until the projects are published. Also it might be worth reading this article as there might be scenarios where you get unexpected results: https://pwmather.wordpress.com/2013/07/22/projectserver-ps2013-ps2010-last-modified-and-last-published-fields-in-pwa-sp2013-ppm-projectonline/