Is there a way to show which calendar a task is using
Hello all, Trying to find out if there is way to show which calendar a task is using. I want a column that will show what calendar each task is assigned. I have a project that uses multiple calen...
- Mar 04, 2022
Hello Tbliss ,
You can insert the "Task Calendar" column - is this what you are looking for or something else?
Paul
Paul_Mather
Mar 04, 2022MVP
Hello Tbliss ,
You can insert the "Task Calendar" column - is this what you are looking for or something else?
Paul
- TblissMar 04, 2022Copper ContributorNope, that is it. I was looking under "calendar" and couldn't find anything. Didn't think to check "Task Calendar". I think this will get me what i need, Thank you!