Is there a way to mass move tasks between Projects?
I'm looking to understand if it's possible to multiple selection tasks and move the data across from one Project to another Project in Project for the Web? Ideally this would include all data like ...
Oct 17, 2022
Kletts --
In the Microsoft Project desktop application, it would be very easy to copy and paste multiple tasks from one project to another. However, as you have already discovered, there is no way to mass move multiple tasks from one project to another. This is simply one more limitation with the new Project for the Web application.
As a work around, you might try the Copy Project functionality to get the tasks into a new project. Hope this helps.
In the Microsoft Project desktop application, it would be very easy to copy and paste multiple tasks from one project to another. However, as you have already discovered, there is no way to mass move multiple tasks from one project to another. This is simply one more limitation with the new Project for the Web application.
As a work around, you might try the Copy Project functionality to get the tasks into a new project. Hope this helps.
Kletts
Oct 17, 2022Copper Contributor
Thanks Dale.
I feared this might be the case, but I'm hopeful as I will give the 'Copying Project' technique a try though so thank you for this. It does in deed help.
I feared this might be the case, but I'm hopeful as I will give the 'Copying Project' technique a try though so thank you for this. It does in deed help.