Is there a way to manage Project Online using PowerShell?

Hi,   Since there isn't a "Project Online" group, I'll try to ask it here: Is there a way to manage Project Online using Powershell?   Wanted to check some resources properties like active and i...
  • jcgonzalezmartin's avatar
    Jul 18, 2016
    Yes, there is. You can use Client Side Object Model for SharePoint Online and Project Online in your PowerShell scripts. However, there are not PowerShell cmdlets for Project Online