Forum Discussion
Bchow509
Sep 14, 2023Copper Contributor
Is there a function in Project Online that replicates Master project and subprojects features?
I believe Project Desktop has a feature that allows you to have a master project and sub-projects. I'm looking to replicate the same thing on Project Online (the app that files only saves on SharePoi...
Bchow509
Sep 15, 2023Copper Contributor
Thank you for that!
I've realized that my org uses Project for the Web App, and with that said, is there a way to link multiple projects into one?
I've realized that my org uses Project for the Web App, and with that said, is there a way to link multiple projects into one?
Kelvin_Kirby
Sep 18, 2023Iron Contributor
Unfortunately this is not built in functionality with Project for the Web. You can use the Roadmap feature but sadly this doesn't provide (at present anyway) anywhere near the same functionality as Project Online.
- Bchow509Sep 19, 2023Copper ContributorAww bummer, thanks!