Is possible to Share resource hours & Availability between multiple PWA
Hi All,
i am using a default PWA from last 5 year and i have created new PWA now, but the resource availability can't be use from old PWA but i have project already schedule in old PWA and some resource need to schedule / use in both PWA.
Is any possibilities to share the resource availability and hours between different PWA.
Thanks
- TjTalha --
No, it is not possible to share resource availability between two PWA instances. Your best bet would be to create a Power BI report that draws the data from both of the PWA instances. Just a thought. Hope this helps.