Forum Discussion

TJTalha's avatar
TJTalha
Copper Contributor
Jan 13, 2022

Is possible to Share resource hours & Availability between multiple PWA

Hi All,

i am using a default PWA from last 5 year and i have created new PWA now, but the resource availability can't be use from old PWA but i have project already schedule in old PWA and some resource need to schedule / use in both PWA.

Is any possibilities to share the resource availability and hours between different PWA.

 

Thanks 

 

  • TjTalha --

    No, it is not possible to share resource availability between two PWA instances. Your best bet would be to create a Power BI report that draws the data from both of the PWA instances. Just a thought. Hope this helps.
  • TjTalha --

    No, it is not possible to share resource availability between two PWA instances. Your best bet would be to create a Power BI report that draws the data from both of the PWA instances. Just a thought. Hope this helps.

Resources