Integration of Microsoft Project schedule on Shop floor

Hi,

 

I am trying to create a production schedule in MS-Project and as of now it appears to be structured in  manner can be implemented at shop floor. I am using Project-3 plan. as of now I am trying to manage this with print of schedules.

 

My question is, I want to share the scheduled plans with users on shop floor, give them access to complete the task and complete etc. So that actual tasks are in sync with MS-Project. 

 

There will be around 20 machines of which I would like the task updates get to entered. How I can accomplish this goal.

 

All support greatly appreciated.

 

 

1 Reply

  • mkjain --

    Give your requirements, I think that the MIcrosoft Project desktop application is the WRONG tool. Instead, I would recommend you consider using Planner Premium (Project for the Web, accessed in Microsoft Teams. Hope this helps.