Forum Discussion
johnhartz8080
Dec 02, 2023Copper Contributor
Integrated Schedules
Hi, I am new to project. I work for a world wide organization and we have various projects from different departments within the organization. I wanted to know if Project will allow me to have in...
John-project
Dec 03, 2023Silver Contributor
First of all, which version of Project do you have (e.g. desktop, Project Online, Project for the Web)?
Assuming you have the desktop version of Project (e.g. Project 2010 through 2021 Pro), then yes, multiple "subprojects" can be integrated into a single master but there are precautions. Depending on the size and complexity of each organization's project, it may make sense to create a single large file with each organizational project as a separate summary.
If you have Project Online, that is an enterprise version of Project and perfectly suited for the scenario your describe.
John