Forum Discussion
Adrian Adam
Jul 21, 2017Tin Contributor
Inactive Tasks show up in Capacity Planning Charts in Resource Center (Project Online)
Hi all
I just noticed the following behaviour which (from my perspective) should be different:
- I added a task in a project and assigned a resource to it, published the project plan
- This task now shows up in the resource's task sheet, it shows up in resource center "Resource Assignments" view and it shows up in resource center "Capacity Planning" diagram
- I inactivated the task and published the project plan again.
- Now the task is still shown in the diagram of the "Capacity Planning" feature which is wrong from my perspective. The other mentioned views do not show it anymore as expected.
Looking forward to your feedbacks :-)
Adrian
4 Replies
- Trutz_StephaniSteel Contributor
Grüzi Adrian,
Looks like a bug to me, too. Did you file a O365 ticket?
Cheers,
Trutz
- Adrian AdamTin Contributor
Hey Trutz
thanks for checking from your side. Yes, it looks like a bug and I opened already a ticket for it. Let's see what will come out :-)
- Adrian AdamTin Contributor
I now got the confirmation that it is a known issue and the Microsoft development team is currently working on a fix.
regards,
adrian