Improper reflection of actual cost of activity
Dale_HowardMVP Yes I am looking at the Task Usage view for looking at actual cost. The screenshot of one of the sample activity is attached. As you can see in the image, the activity is started in Mar-21, but its cost is coming in May-21.
If I may throw in my two cents.
Unfortunately your screen shot doesn't show the whole picture. For example, it doesn't show the assignments for the "Foundation including PCC" task.
I can create a similar screen shot but it may or may not be due to the same reason. In this particular case, Project does NOT calculate costs and assignment actual cost is manually entered.
I also notice that you must have a custom calendar and/or work hours since the duration is in partial days and with a Standard calendar, a start date of 3/3/21 with a duration of 59.75 days does not give a finish date of 5/17/21 ( your baseline finish) or 7/26/21 (your finish date). Also, what is your fiscal year setting?
How are you updating progress? Are you using resource leveling? Do you have any task splits? There are a number of factors that may cause your actual cost to appear as it does, we just need more information about your plan in order to help figure out what's going on. In addition to showing more data on the Task Usage view, a screen shot of your Gantt Chart may also help.