Forum Discussion
AjayAgrawal
Apr 02, 2021Copper Contributor
Improper reflection of actual cost of activity
Hii, I am facing an issue while updating project progress in MSP. For instance, if an activity has started in say month of Mar-21, I am putting the actual start date and remaining duration/actual...
Apr 02, 2021
Ajay -- How do you know that the cost is coming in the future? Where do you see this? Are you looking at the Task Usage view? It would help if you could include a screenshot of your project so we can see what you see. Let us know. Thanks!
AjayAgrawal
Apr 03, 2021Copper Contributor
Dale_HowardMVP Yes I am looking at the Task Usage view for looking at actual cost. The screenshot of one of the sample activity is attached. As you can see in the image, the activity is started in Mar-21, but its cost is coming in May-21.