Importing a plan from Google Sheet
Hi, Earlier I was using Smartsheet project management tool and now corporate has moved us into MS Project Online. I had exported a Smartsheet plan into Google Sheet. How do I import the Google...
- Jul 21, 2022Robert --
I ran into this exact problem when I exported a project from Project for the Web to an Excel workbook. When I tried to import the workbook into Microsoft Project, the From: Excel field rows were blank in the Import Wizard dialog.
Oddly enough, I was able to resolve the problem by copying and pasting the contents of the original Excel workbook into a totally new blank workbook and then saving it with a different name. I would suggest that you try this method to see if it resolves your problem as well. Hope this helps.
John-project
Jul 22, 2022Silver Contributor
robertpoddar,
You're welcome and thanks for the feedback. Please mark Dale's response as the answer.
John
You're welcome and thanks for the feedback. Please mark Dale's response as the answer.
John