Forum Discussion
robertpoddar
Jul 13, 2022Copper Contributor
Importing a plan from Google Sheet
Hi, Earlier I was using Smartsheet project management tool and now corporate has moved us into MS Project Online. I had exported a Smartsheet plan into Google Sheet. How do I import the Google...
- Jul 21, 2022Robert --
I ran into this exact problem when I exported a project from Project for the Web to an Excel workbook. When I tried to import the workbook into Microsoft Project, the From: Excel field rows were blank in the Import Wizard dialog.
Oddly enough, I was able to resolve the problem by copying and pasting the contents of the original Excel workbook into a totally new blank workbook and then saving it with a different name. I would suggest that you try this method to see if it resolves your problem as well. Hope this helps.
Jul 19, 2022
Robert --
John's reply helped me to figure out what might be your problem. When you go to import the Excel workbook, only select the Tasks option in the Import Wizard dialog. If you select Tasks, Resources, and Assignments, then you Excel workbook MUST have three worksheets. Most of the time, you can successfully import an Excel workbook only using the Tasks option. Just a follow up to John's excellent post. Hope this helps.
John's reply helped me to figure out what might be your problem. When you go to import the Excel workbook, only select the Tasks option in the Import Wizard dialog. If you select Tasks, Resources, and Assignments, then you Excel workbook MUST have three worksheets. Most of the time, you can successfully import an Excel workbook only using the Tasks option. Just a follow up to John's excellent post. Hope this helps.
robertpoddar
Jul 21, 2022Copper Contributor
OK Dale.. i did try out what John mentioned, but i am yet unsuccessful. I have shared the screenshots of the Map Wizard as part of John's response.
- robertpoddarJul 22, 2022Copper ContributorThank you so much 🙂
- Jul 22, 2022Robert --
You are more than welcome for the help, my friend. 🙂 - robertpoddarJul 22, 2022Copper ContributorHi Dale,
Your solution worked!! .. thank you so much. The import wasn't clean in terms of the right columns getting imported, but the original issue of not being able to import is resolved.
Thank you so much..
Will work on streamlining the mapped data to get the desired results. - Jul 21, 2022Robert --
I ran into this exact problem when I exported a project from Project for the Web to an Excel workbook. When I tried to import the workbook into Microsoft Project, the From: Excel field rows were blank in the Import Wizard dialog.
Oddly enough, I was able to resolve the problem by copying and pasting the contents of the original Excel workbook into a totally new blank workbook and then saving it with a different name. I would suggest that you try this method to see if it resolves your problem as well. Hope this helps.