Forum Discussion
rohanw24
Sep 25, 2021Brass Contributor
Import MS Project 2010 projects to Project Online
Hello Everyone,
Is there any other way to import MS Project 2010 projects to Project Online other than MS Project Professional Import Wizard? We need to consider below factors:
1. Bulk transfer of 200+ projects.
2. There are lot of task custom fields. We should be able to transfer this data without any issue.
Thanks & Regards,
Rohan
1 Reply
Hello rohanw24 ,
Are you using Project Server 2010? If so, you can automate this using a tool such as Fluent Books: https://fluentpro.com/fluentbooks-for-project-server
This is a paid for tool, there isn't a free migration tool available that I'm aware of.
Paul