Forum Discussion
How to turn off notes “multiple line” message (MS Project 2013)
- Apr 05, 2021
I've been using Project in various versions for over 20 years and I've never seen that message and it took me a while to figure out how to even make the message appear. The reason it appears is that at some point a user entered multiple lines of Notes field text via the Notes tab of the Task Information window. That's the only way, other than through VBA, a user can create multiple lines of text. Once those multiple lines of notes text exist for a given task, attempting to edit the notes text via the Notes field as a column in a view, will trigger the message.
The answer to your question is, you cannot enter further Notes field text via the Notes field directly, you must either convert all task Notes field text to single lines of text less than 255 characters with no carriage returns, or only enter Notes field text via the Task Information window. I suggest you do the latter as that will allow you to take full advantage of Notes field editing capabilities (i.e. font formatting, multiple lines, bulleted lists, ability to insert objects like an Excel table, text from a Word document, or images).
John
- shaunavApr 05, 2021Copper ContributorI’m using a desktop version of MS Project 2013. I’ve added a Notes column to the right of Resource Names in the Gantt Chart view and enter the notes there. I add to them each week when the team meets (and in between if I receive any pertinent info).
I would LOVE to get rid of this annoying popup. It only happens when the text string gets long. Any help appreciated.
- John-projectApr 05, 2021Silver Contributor
I've been using Project in various versions for over 20 years and I've never seen that message and it took me a while to figure out how to even make the message appear. The reason it appears is that at some point a user entered multiple lines of Notes field text via the Notes tab of the Task Information window. That's the only way, other than through VBA, a user can create multiple lines of text. Once those multiple lines of notes text exist for a given task, attempting to edit the notes text via the Notes field as a column in a view, will trigger the message.
The answer to your question is, you cannot enter further Notes field text via the Notes field directly, you must either convert all task Notes field text to single lines of text less than 255 characters with no carriage returns, or only enter Notes field text via the Task Information window. I suggest you do the latter as that will allow you to take full advantage of Notes field editing capabilities (i.e. font formatting, multiple lines, bulleted lists, ability to insert objects like an Excel table, text from a Word document, or images).
John
- shaunavApr 05, 2021Copper Contributor
Thanks John-project. Someone owned the most troublesome project plan before I took it over, so perhaps they did use multiple lines (although it doesn't appear that way now). Time to rebuild the plan!
As to using the Task Information window, I don't need formatting and my notes are quite cryptic; I add the most recent in front of what's already there (so we see most recent note from the Gantt view); I separate with a semicolon. I appreciate your insights. Thanks again.
- shaunavApr 01, 2021Copper Contributor
desktop version. Just closed my laptop for 3-day weekend; will get that to you on Monday. Thanks!