how to show outline code description in excel visual reports
when i use excel visual report i find only the outline code value only appears in the report and don't find the description of it I need help about this subject please.
John-project
Jun 05, 2023Silver Contributor
Matef89,
As far as I know, Visual Reports does not include the description property of an Outline Code. However, an export to Excel using VBA can include the Outline Code description property.