How to shift action bar at the beginning
Hi all, Sometimes happens something like that: - I set a link with the previus and following action - I set a duration - I force the end of the action (longer of the once previusly planned) this...
Dariocg
May 02, 2022Copper Contributor
what do you mean with "insert a lead or lag"? can I have an example?
thank you
thank you
John-project
May 02, 2022Silver Contributor
Wow, where have you been for two weeks?
This example shows a 10 day lag on task c and a 2 day lag on the milestone.
John
- DariocgMay 02, 2022Copper ContributorOk, I see… I was wondering something different. Try to imagine you have a deadline on 27th of may. Instead to have lag of number of days I’d like to have lag depending of a proper date. In this way, if I move previous task, my deadline remains still the same.
I don’t know if it is clear
(I missed your reply ☺️)- John-projectMay 02, 2022Silver Contributor
Project has a Deadline field that can be used as a reference for a task or milestone. In this example all tasks are dynamic, allowing them free movement. The deadline shows graphically how close the finish milestone is to the deadline. Is that what you want? If not, please explain in more detail.
John