Forum Discussion
Dariocg
Apr 11, 2022Tin Contributor
How to shift action bar at the beginning
Hi all, Sometimes happens something like that: - I set a link with the previus and following action - I set a duration - I force the end of the action (longer of the once previusly planned) this...
John-project
Apr 11, 2022Silver Contributor
Dariocg,
When you "force the end" I assume you mean you are directly entering later date in the Finish field. That sets a finish-no-earlier-than constraint on the task and pushes it to the end of the span.
Directly entering dates into either th Start or Finish fields is bad practice because it does set a constraint and that interferes with Project's ability to create a dynamic schedule. If you want the task to have a delay I suggest you insert a lead or lag as appropriate.
John
When you "force the end" I assume you mean you are directly entering later date in the Finish field. That sets a finish-no-earlier-than constraint on the task and pushes it to the end of the span.
Directly entering dates into either th Start or Finish fields is bad practice because it does set a constraint and that interferes with Project's ability to create a dynamic schedule. If you want the task to have a delay I suggest you insert a lead or lag as appropriate.
John
- DariocgMay 02, 2022Tin Contributorwhat do you mean with "insert a lead or lag"? can I have an example?
thank you- John-projectMay 02, 2022Silver Contributor
Wow, where have you been for two weeks?
This example shows a 10 day lag on task c and a 2 day lag on the milestone.
John
- DariocgMay 02, 2022Tin ContributorOk, I see… I was wondering something different. Try to imagine you have a deadline on 27th of may. Instead to have lag of number of days I’d like to have lag depending of a proper date. In this way, if I move previous task, my deadline remains still the same.
I don’t know if it is clear
(I missed your reply ☺️)