How to ret resource capacity for more than 1 year from now
Hello, I am developing a report that displays company's workload for some years ahead. I use ResourceTimephasedDataSet endpoint to get data, but I found that it is limited by 12 months from now, I d...
- May 18, 2021
Hello Slava_Sha ,
This is controlled by the Resource Capacity Settings found in PWA Settings > Additional Server Settings. The Months Ahead setting by default is set to 12, update this setting as required. Then once the "Reporting (Resources Capacity Range Sync)" next runs, which is once a day, you will find the capacity data is updated.
Paul
Paul_Mather
May 18, 2021MVP
Hello Slava_Sha ,
This is controlled by the Resource Capacity Settings found in PWA Settings > Additional Server Settings. The Months Ahead setting by default is set to 12, update this setting as required. Then once the "Reporting (Resources Capacity Range Sync)" next runs, which is once a day, you will find the capacity data is updated.
Paul
- Slava_ShaMay 18, 2021Tin Contributor