How to plot critical tasks in a .pdf or .ppt?

 

I would like tips to be able to print the critical tasks of the project like this case below. However, I would like them all to fit on the same page, what is the best way?

 

 

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    FernandoFalchiane

    You might try the following.

    1. Apply a filter for critical tasks

    2. Use the Zoom control (View > Zoom group > Zoom) to size the image to a single page

    3. Go to, Task > Clipboard group > Copy > Copy Picture and select "To GIF image file".

    4. Copy and paste that image to PowerPoint.

    5. Or, after filtering and zooming you could simply do a screen shot and paste that into PowerPoint.

     

    Hope this helps.

    John