how to open customize an existing projects site template in project server 2019 ?

In project server 2019 when publish any project then its site also created.   Please let me know how to customize the projects sites template then the every site will be effect.
  • Paul_Mather's avatar
    Paul_Mather
    May 10, 2023

    Hello Basim2245 ,

    Our posts must have crossed. To update the existing project site template, create a site from the template using the SharePoint Site Contents page New > Subsite:

     

    Fill out the form, on the template selection section, select the template, previously created custom templates are on the Custom tab. If you do not have a custom template, use the Project Site template.
    Make the changes to the newly created site and save that as a template. Then add that new site template to the EPT. From that point onwards, newly created projects will have project sites created from the new template.

    Paul