Forum Discussion
how to open customize an existing projects site template in project server 2019 ?
- May 10, 2023
Hello Basim2245 ,
Our posts must have crossed. To update the existing project site template, create a site from the template using the SharePoint Site Contents page New > Subsite:
Fill out the form, on the template selection section, select the template, previously created custom templates are on the Custom tab. If you do not have a custom template, use the Project Site template.
Make the changes to the newly created site and save that as a template. Then add that new site template to the EPT. From that point onwards, newly created projects will have project sites created from the new template.Paul
When you customize the SharePoint project site template, this action will only impact new projects when they are created in Project Server 2019. You will need to manually update existing project site templates. Sorry, but hope this helps.
- Paul_MatherMay 10, 2023MVP
Hello Basim2245 ,
Our posts must have crossed. To update the existing project site template, create a site from the template using the SharePoint Site Contents page New > Subsite:
Fill out the form, on the template selection section, select the template, previously created custom templates are on the Custom tab. If you do not have a custom template, use the Project Site template.
Make the changes to the newly created site and save that as a template. Then add that new site template to the EPT. From that point onwards, newly created projects will have project sites created from the new template.Paul