Forum Discussion

Dariocg's avatar
Dariocg
Copper Contributor
May 02, 2022

How to manage real time for activity and safety

Hi,

usually I have activities with a proper duration (i.e. 30 days) but my PM gives me a safety end (i.e. 60 days).

 

Is there any way to set both? I'd like to set 30 days and at the same time having all the other linked activities starting after the safety date (I don't like to set delay on the other activities).

 

Hope it is clear what i'm saying...


Thanks

2 Replies

  • Dariocg --

    My solution is based on two assumptions:

    1. You are using the Professional version of the Microsoft Project desktop application.
    2. You are linking all detailed tasks and milestones with Predecessors and Successors.

    If you meet the two assumptions above, here is what you could do. Suppose the task in question is named Design and you have set a Duration value of 30 days. Immediately after the Design task, insert a new task named Design Safety, and set the Duration of this task as 30 days as well. Then link the Design task, the Design Safety task, and the following task with a Finish-to-Start dependency relationship. Click the Design Safety task to select it. In the Schedule section of the Task ribbon, click the Inactivate button to temporarily "cancel" the Design Safety task.

    If the Design task starts going very late, you can reactivate the Design Safety task. Hope this helps.
    2.
    • Dariocg's avatar
      Dariocg
      Copper Contributor
      thank you. I was wondering in something different, but it could work.