How to "link up" to set a Start to Finish type in predecessors?

Good afternoon,   I have a Project with over 80 tasks and many summaries. I am trying to "link up" to have link type be Start to Finish (SF) for tasks 67 & 48. What I want is for task 48 to start 3...
  • John-project's avatar
    John-project
    Jul 11, 2022

    Karine0918 

    Unfortunately the note you superimposed over the screen shot blocks out vital information I need to replicate that part of your plan. Also it looks like there is an error in the note, it talks about task 57 which is not shown. I assume you meant task 67.

     

    I also note the you show a link to a summary line (i.e. task ID 62). That is a no-no. Never place predecessors or successors on summary lines. Summary lines are not tasks, they are simply a summary of the subtasks under them.

     

    Based on what I could see, this rendering of your plan should at least get you pointed in the right direction.