Forum Discussion
MichalPaulo
Apr 27, 2023Copper Contributor
How to integrate Ms Project Online Desktop Client with Ms Teams Project App and Todo Planner?
Hello All, I am looking for a way to integrate my desktop Project client with Teams. Couple of questions that arised: I am working in desktop client. Can I save and have an immediate integration ...
- Apr 28, 2023MichalPaulo --
1. If you are working with the Microsoft Project desktop application, then no, this is not possible. If you want this kind of integration with Teams, you would need to downgrade to the Project for the Web application.
2. No, you cannot export any type of project information from Project for the Web into the Microsoft Project desktop application.
Hope this helps.
Apr 28, 2023
MichalPaulo --
1. If you are working with the Microsoft Project desktop application, then no, this is not possible. If you want this kind of integration with Teams, you would need to downgrade to the Project for the Web application.
2. No, you cannot export any type of project information from Project for the Web into the Microsoft Project desktop application.
Hope this helps.
1. If you are working with the Microsoft Project desktop application, then no, this is not possible. If you want this kind of integration with Teams, you would need to downgrade to the Project for the Web application.
2. No, you cannot export any type of project information from Project for the Web into the Microsoft Project desktop application.
Hope this helps.
- MichalPauloApr 28, 2023Copper Contributor
Thanks Dale_HowardMVP
This is quite sad news.
I am still working on how to automate my work between Todo Planner and Desktop Project.
I think this is possible Web->Desktop by exporting data to Excel file and Desktop->Web by using Power Automate. Did not find out how to exactly do that yet.