Forum Discussion
Magnus88
Feb 12, 2020Copper Contributor
how to import a planner project into project?
God day. We initially made our project in Planner. This was not sufficient regarding project managing. We now got Project, is there a way to use our existing planner tasks in project? There...
Domlit
Feb 23, 2023Brass Contributor
It's a faff but one migration path (assuming you want to use PFTW) if to export the planner to Excel, get a P3 License from your org that allows for you to use project desktop, copy tasks from Excel to Project desktop then upload that MPP file to PFTW. There is a similar MPP import function for Project Online. If you are just using Project Desktop then stop at the desktop point.