Forum Discussion

ThePM-CA's avatar
ThePM-CA
Brass Contributor
Jun 23, 2022
Solved

How to have two tasks start on same day

Hi 

 

I am trying to have two tasks start on same day both linked to each other. So this is what I tried:

 

Two task example

   Task A    06/23/2022  06/23/2022  1 day

   Task B    06/23/2022  06/23/2022  1 day

   Task C    06/23/2022  06/23/2022  1 day  

 

What I initially did is I copied the end date of the first and did a paste special as object to the start of Task B and that worked. I did even have the predecessors too.

 

But when I tried to add more that technique didn't worked out. 

 

The only time I can have all tasks start on the same day / date is when I do not link them or remove predecessors 

 

Any advise will be much appreciated.

 

Thanks,

 

 

  • Hello ThePM-CA ,

    What about changing the relationship type to Start to Start:

    To do this, either:

    • Double click the task and use the Task Information window then on the Predecessors tab change the Type as seen below:

    Or:

    • Click in the Predecessors field, press F2 to put the cell in edit mode then type SS after the task ID:

    I hope that helps

    Paul

2 Replies

  • Hello ThePM-CA ,

    What about changing the relationship type to Start to Start:

    To do this, either:

    • Double click the task and use the Task Information window then on the Predecessors tab change the Type as seen below:

    Or:

    • Click in the Predecessors field, press F2 to put the cell in edit mode then type SS after the task ID:

    I hope that helps

    Paul